Energy Policy 101: How the Movement of Electrons is Regulated

December 12, 2016
Energy Policy 101

Energy policy development is complicated.   Recall that the electric industry has been regulated for more than 100 years and it remains highly regulated today, even with competitive markets.  Moreover, both the Federal government and States have roles to play in regulation.  Using examples, this article focuses on federal jurisdiction over “wholesale” electricity that flows across state lines and is not sold for direct consumption to end users.  Sales to end users, including authorization of competitive retail suppliers, is the exclusive jurisdiction of the states.

In the U.S., policy at the highest level is established by Acts of Congress and the President.  It is implemented by the executive branch including the Federal Energy Regulatory Commission (FERC) and the Department of Energy (DoE).  This policy establishes a framework for the tariffs that govern the use of the nation’s electric transmission grid.  It is useful to think of this framework as a “top down” process.  The owners and operators of the transmission grid, in turn, submit tariffs that comply with the law and policy to FERC for approval.  The development of tariffs is a “bottom up” process.

Three examples of the biggest orders to come out of FERC during President Obama’s administration include FERC Order 745, which required ISOs and RTOs to pay customer-side capacity resources such as demand response an equivalent value to what power plants and other supply-side resources earn; FERC Order 755, which required ISOs to create programs to reward “fast-responding” resources such as batteries for frequency regulation; and FERC Order 1000, which has set up a new regime for transmission operators and utilities to plan for, and pay for, regional grid investments.

The FERC has been instrumental in creating Regional Transmission Operators (RTOs) through policy decisions.  RTOs and Independent System Operators (ISOs) have largely eliminated the need to set wholesale electricity prices by a fixed tariff and instead allow prices to be established by markets.  The detailed implementation of electric policy is done at the RTO level. FERC’s decisions and orders apply to the tariffs of ISOs and RTOs that run much of the U.S. power grid. About 70 percent of the country is served by ISOs and RTOs, which fall under federal jurisdiction because they cross state lines.

The shift to RTOs has not eliminated the need for regulation of electricity.  Instead it has shifted the regulatory focus from setting prices to setting market rules.  The market rules are embodied in the RTO tariffs.  The FERC is responsible for approving the RTO tariffs.  The RTO tariffs are developed with varying degrees of stakeholder input, depending on the RTO itself.  The basic process follows the steps from stakeholder consideration to RTO and final review and approval by FERC using stakeholder input as shown below:

policy-process

Each RTO handles stakeholder consideration differently. PJM Interconnection, for example, is the only RTO that is required to accept stakeholder recommendations as determined by a vote – at least on some issues.  Other RTOs simply consider the input of stakeholders and file what they think best.  There is little doubt that PJM has the most robust process. Most issues are addressed through a series of meetings that follow a set process.  The process is not unlike a government legislative body with committees, subcommittees, etc.  Often stakeholders reach consensus and many issues are resolved with no or nominal opposition.

Demand Response Policy Considerations

Perhaps one major exception to consensus pertains to issues involving capacity market design, including Demand Response (DR) participation.  On these issues, stakeholders are typically split between generation owners – including incumbent utilities – and load interests.  This is because any changes that reduce the opportunity for generation participation or revenue leads to reduced income for generators.  Such changes include enabling competitive resources such as DR and reductions in overall capacity requirements.

Conversely, stakeholders representing users of electricity oppose changes that increase costs without a credible probability of improving reliability.  As a result, most controversial issues have competing proposals.  Stakeholder votes are allocated in such a way that a required two-thirds’ supermajority (this applies to PJM) for approval of contested changes is difficult to reach.   A deadlocked stakeholder process allows PJM to file changes that may not have broad stakeholder support.  RTOs are non-profit entities without a commercial stake in market outcomes.  However, as organizations, PJM and other RTOs have an inherent bias toward “reliability” which often results in costly requirements for more resources, especially conventional generation.

Stakeholders that oppose an RTO filing have the opportunity to “protest” the tariff changes at FERC.  FERC need only determine that a filing is “just and reasonable”. While ostensibly the “just and reasonable” standard may include cost considerations, FERC, like PJM and other RTOs, also has a bias toward reliability and often will accept the RTO filing regardless of cost implications.

FERC Decisions and the Appeals Process

FERC decisions can be appealed to the federal courts on the basis non-compliance with the governing law, or an “arbitrary and capricious” decision.  Appeals Courts avoid ruling on the substance of a FERC ruling because this can place the Court in the position of creating laws and regulations.  Appeals Court decisions can be appealed to the Supreme Court as occurred in the high-profile case of FERC Order 745.  In particular, owners of conventional generation (the petitioners) opposed the Order because the treatment of demand response threatened their revenues and they took FERC to court.  The case hinged primarily on the issue of state versus federal jurisdiction (was the Order consistent with the Federal Power Act’s provisions designating retail rate setting as the exclusive jurisdiction of the states?).

In a major victory for the DR industry, the U.S. Supreme Court upheld FERC Order 745 via a 6-2 decision in January 2016, reversing a lower court opinion that found that it violated states’ jurisdiction over retail energy pricing, and dealing a blow to the utility group that brought the original lawsuit. DR providers and environmental groups supported FERC Order 745, noting that it has opened markets that have brought significant new demand-side capacity to the country’s grid operators for use in controlling the wholesale grid. Order 745 also helped reduce the need for fossil fuel-fired power and lowered overall electricity costs for consumers. But the underlying legal question behind the lawsuit — the bounds between federal and state jurisdiction over energy markets — could be modified by Acts of Congress.

You can see why the process of defining energy policy can be extremely complicated in practice. CPower takes a leadership role in shaping market transformation and regulatory reform, while working hard to maximize program benefits for our customers. It’s imperative that our Market Development team constantly stays abreast about regulatory processes as thought leaders in the DR community. These efforts enable us to provide services that take the complexity out of DR participation within the context of changing program rules, while optimizing your energy savings and earnings. This will become increasingly critical as energy markets continue to transform in the near future.

Published by

Avatar

Bruce Campbell

Mr. Campbell is Director of Regulatory Affairs at CPower. He is an expert in regulatory proceedings and market design with 40 years of experience in the electric industry including generating station management and strategic development. He has been an active participant in the stakeholder process of regional grid operators for over 15 years while representing generation owners and transmission owners as well as his current employer. Prior to joining CPower via EnergyConnect, Mr. Campbell managed regulatory affairs with a particular focus on market design and RTO development for Mirant, an independent generation owner and for Pepco, an investor owned utility. Mr. Campbell holds a BS degree in Mechanical Engineering from Bucknell University in Pennsylvania.

Avatar
Bruce Campbell

Mr. Campbell is Director of Regulatory Affairs at CPower. He is an expert in regulatory proceedings and market design with 40 years of experience in the electric industry including generating station management and strategic development. He has been an active participant in the stakeholder process of regional grid operators for over 15 years while representing generation owners and transmission owners as well as his current employer. Prior to joining CPower via EnergyConnect, Mr. Campbell managed regulatory affairs with a particular focus on market design and RTO development for Mirant, an independent generation owner and for Pepco, an investor owned utility. Mr. Campbell holds a BS degree in Mechanical Engineering from Bucknell University in Pennsylvania.

Skip to content